Battle River REA
System Status
April 18, 19, 20 & 21, 2007
Status as of Apr 21, 2007 - 8:30 p.m.Hrs
Overview
On April 18, 2007 at approximately 11:00 Hrs a snow and ice storm caused major damage to our distribution system.
In total we have experienced 20 miles of major line damage to the system this includes between 80 and 100 broken poles. This portion of line will require a complete rebuild of the conductor and the majority of the poles.
This storm caused power outages to more than of 600 REA members
We have BRREA staff and five mutual aid crews working on the repairs. These crews are using the traditional line equipment with three Nodwells to support the difficult weather conditions.
At the current rate of repair we expect to have the majority of the repairs completed by the end of the day on April 20, 2007. (Updated to End of Day April 21, 2007) (Updated to End of Day April 22, 2007)
BRREA staff have completed inspections on the distribution system to determine the magnitude of the damage.
Repairs and restoration to date to approximately 200 members in the areas identified below
Status: Repairs and restoration including unplanned outages identified today approx. 300
Status: Repairs and restoration including unplanned outages identified today approx 491
Area Detail and Information
Camrose East:
Rebuild is approx. 16 miles of single phase
(12 Miles in one section along Hwy 26)
Members affected 400
Estimated repair completed by Apr 21 at 12:00 Hrs
Status: Rebuilt Approx 7 miles
Re-energized the majority of this area – with only 40 remaining off
Revised schedule for completion Apr 22 at the end of day
Roundhill East: (Main Line)
Rebuild 0.5 miles of three Phase Line
A change in the damage was upgraded to 3 miles
Members experiencing a power outage 100
Estimated repair completed Apr 20 by 12:00 Hrs
Status: Line energized Apr 20 by 20:00 Hrs
Two rural substations energized
Service restored to Approx 75 members
Roundhill East (Hampton Area):
This area is down stream from the Round Hill Three Phase
Repair/replace 5 miles of Single Phase Line
Members experiencing a power outage 100
Estimated repairs to be completed Apr 21 by end of day
Status: Crews are working on the repairs
Service restored to 96 customers
Estimated repairs to most members to be completed Apr 22 by end of day
Fort/Chipman/Bruderheim Areas
Additional damage was identified today, 10 poles require replacement
Approx 5 miles of line requires major repair
Members experiencing a power outage 20
Scheduled for completion Apr 21 by the end of day
Status: Two crews are working in this area
Service restored to 16 customers
Power Restoration Area Detail
Camrose West
Repair 1 conductor break
Members experiencing a power outage 60
Estimated repair completed Apr 19 by 22:00 Hrs
Repairs complete Apr 20
Service restored to all customers
Bashaw East
Fortis line damage
Members experiencing a power outage 20
Estimated repair completed by Apr 19 22:00 Hrs
Repairs complete Apr 19
Service restored to all customers
Bashaw/Ferintosh/Meeting Creek
Replaced fuses/reset OCR’s
Members experiencing a power outage 100
Repair completed by Apr 19 12:00 Hrs
Repairs complete Apr 19, 07
Service restored to all customers
Viking Area
Replaced fuses
Members experiencing a power outage 15
Repair completed by Apr 19 01:00 Hrs
Daysland
Replaced fuses
Members experiencing a power outage 10
Repair completed by Apr 19 17:30 Hrs
Lougheed North
Rebuild 0.5 miles of single phase line
Members experiencing a power outage 20
Estimated repair completed by Apr 21 12:00 Hrs
Repairs complete Apr 20
Service restored to all customers
Fort/Chipman/Bruderheim Areas
Replaced fuses
Members experiencing a power outage 50
Repair completed by Apr 19 17:00 Hrs
Yours truly,
BATTLE RIVER RURAL ELECTRIFICATION
ASSOCIATION LIMITED
PER:
COLLEEN MUSSELMAN,
General Manager
cc Board of Directors