RURAL ELECTRIFICATION ASSOCIATION  LTD.

            Box 1420, Camrose, Alberta  T4V 1X3

Phone:  780-672-7738      Fax:  780-672-7969

Toll Free:  1-877-428-3972

Website:  www.battleriverrea.com

E-mail:  colleen-brrea@telus.net

 

 

  Battle River REA

System Status

 

April 18, 19, 20 & 21, 2007

 

Status as of Apr 21, 2007 - 8:30 p.m.Hrs

 

 

 

Overview

 

On April 18, 2007 at approximately 11:00 Hrs a snow and ice storm caused major damage to our distribution system.

 

In total we have experienced 20 miles of major line damage to the system this includes between 80 and 100 broken poles. This portion of line will require a complete rebuild of the conductor and the majority of the poles.

 

This storm caused power outages to more than of 600 REA members

 

We have BRREA staff and five mutual aid crews working on the repairs. These crews are using the traditional line equipment with three Nodwells to support the difficult weather conditions.

 

At the current rate of repair we expect to have the majority of the repairs completed by the end of the day on April 20, 2007. (Updated to End of Day April 21, 2007) (Updated to End of Day April 22, 2007)

 

BRREA staff have completed inspections on the distribution system to determine the magnitude of the damage.

 

Repairs and restoration to date to approximately 200 members in the areas identified below

Status: Repairs and restoration including unplanned outages identified today approx. 300

Status:  Repairs and restoration including unplanned outages identified today approx 491

Area Detail and Information

 

Camrose East:

            Rebuild is approx. 16 miles of single phase

(12 Miles in one section along Hwy 26)

            Members affected 400

            Estimated repair completed by Apr 21 at 12:00 Hrs

 

Status: Rebuilt Approx 7 miles

             Re-energized the majority of this area – with only 40 remaining off

             Revised schedule for completion Apr 22 at the end of day

 

 

Roundhill East: (Main Line)

            Rebuild 0.5 miles of three Phase Line

            A change in the damage was upgraded to 3 miles

Members experiencing a power outage 100

            Estimated repair completed Apr 20 by 12:00 Hrs

 

Status:  Line energized Apr 20 by 20:00 Hrs

             Two rural substations energized             

             Service restored to Approx 75 members

 

 

Roundhill East (Hampton Area):

            This area is down stream from the Round Hill Three Phase       

Repair/replace 5 miles of Single Phase Line

            Members experiencing a power outage 100

            Estimated repairs to be completed Apr 21 by end of day

 

Status: Crews are working on the repairs

             Service restored to 96 customers

             Estimated repairs to most members to be completed Apr 22 by end of day

 

Fort/Chipman/Bruderheim Areas

            Additional damage was identified today, 10 poles require replacement

             Approx 5 miles of line requires major repair

 Members experiencing a power outage 20

             Scheduled for completion Apr 21 by the end of day

 

Status: Two crews are working in this area

             Service restored to 16 customers

 

 

 

 

Power Restoration Area Detail

 

Camrose West

            Repair 1 conductor break

            Members experiencing a power outage 60

            Estimated repair completed Apr 19 by 22:00 Hrs

 

Repairs complete Apr 20

             Service restored to all customers

 

 

 

 

 

Bashaw East

            Fortis line damage

            Members experiencing a power outage 20

            Estimated repair completed by Apr 19 22:00 Hrs

 

Repairs complete Apr 19

             Service restored to all customers

 

Bashaw/Ferintosh/Meeting Creek        

Replaced fuses/reset OCR’s

            Members experiencing a power outage 100

            Repair completed by Apr 19 12:00 Hrs

 

Repairs complete Apr 19, 07

             Service restored to all customers

 

Viking Area

            Replaced fuses

            Members experiencing a power outage 15

            Repair completed by Apr 19 01:00 Hrs

 

Daysland

            Replaced fuses

            Members experiencing a power outage 10

            Repair completed by Apr 19 17:30 Hrs

 

Lougheed North

            Rebuild 0.5 miles of single phase line

            Members experiencing a power outage 20

            Estimated repair completed by Apr 21 12:00 Hrs

 

Repairs complete Apr 20

             Service restored to all customers

 

Fort/Chipman/Bruderheim Areas

            Replaced fuses

            Members experiencing a power outage 50

            Repair completed by Apr 19 17:00 Hrs

 

 

 

 

Yours truly,

 

BATTLE RIVER RURAL ELECTRIFICATION

ASSOCIATION LIMITED

 

PER:

 

 

COLLEEN MUSSELMAN,

General Manager

 

cc            Board of Directors